The MAG transformation programme was announced in 2015 and originally scheduled to open in Summer 2020, but the project was delayed due to the COVID-19 pandemic, officially opening on July 14th, 2021. Fortunately, ADXBA had already completed the design process (including the mechanical and structural engineering designs for the LED display’s supporting steelwork) before the pandemic struck, so the team was able to take advantage of the reduced site activity during lockdown to complete the installation and commissioning of the displays to the highest standard, including meticulously cladding the perimeter of the giant LED display so that it blends seamlessly into the physical space. The result is a high-impact installation that ADXBA’s operations director, Gareth Tuxworth, describes as, “Our proudest achievement to deliver our largest indoor display with quality high on the agenda.”